To Content
  • BGAA Penkun

  • Biogas membrane system Penkun for 1.400 m³ biogas process design, detail engineering, prefabrication and plant construction, commissioning and service

  • Customer

    Landwärme GmbH, Ungererstraße 40, 80802 München

    Order Type

    General Contractor

    Construction time

    11/2015 - 07/2016

  • Spülung, Wartung und wiederkehrende Prüfung Soleleitung

  • Maintenance and treatment of valves and shaft structures, repair of PE HP-gravity pipelines DN 1200

  • Customer

    DBE mbH, Eschenstraße 55, 31224 Peine

    Order Type

    General Contractor

    Construction time

    10/2015 - 02/2016

  • Inbetriebnahme Fockbek-Ellund

  • Feeding of natural gas from the "DEUDAN" line into the newly constructed line with a operating pressure of 60 bar

  • Customer

    N.V. Nederlandse Gasunie, Concourslaan 17, 9700 MA Groningen

    Order Type

    General Contractor

    Construction time

    08/2015 - 08/2015